aqua + H

Well Restoration Budget

Zipolite

Oaxaca, México

Material and labor costs for the restoration of HRIBANIKA’S well along with solar powered equipment to mobilize the complex with drinking and tap water. Budget composed by HRIBANIKA’s founder Angélica Tonalkiahuitl and myself. This outline is an educated approximation of materials and labor; solar equipment providers and raw materials vendors, etc. are subject to change as crytpo solutions are currently pursued with high priority.

 

PHASE 1: WELL REINFORCEMENT

12 concrete rings are required to reinforce the circumference of the existing concrete well at depth, which requires rental of a mold:

Mold Rental = $800 per day

Producing 1 mold per day x 12 days of renting

MOLD RENTAL TOTAL = $9,600 MXN / $483 USD

The cost of labor to create the new reinforcing rings = $1,500 per day x 12 days:

TOTAL CONCRETE RING PRODUCTION LABOR = $18,000 MXN / $906 USD

The cost of labor to install the 12 rings inside the well = $3,500 per 1 per ring:

TOTAL CONCRETE RING INSTALLATION = $42,000 MXN / $2,112 USD

 

To create the concrete rings — an average of 1 ton of cement, 1 truckload of gravel and 1 truckload of sand is needed:

1 ton of cement = $4,200

1 truckload of gravel dump = $3,200

1 truckload of sand = $2,200

MATERIALS TOTAL = $9,600 MXN / $483 USD

 

The cost to haul the materials to HRIBANIKA from the materials site = $500 per person; it takes 3 people to haul these quantities in one work week

Hauling Cost = $1,500 per day x 6 days

TOTAL HAULING COSTS = $9,000 MXN / $475 USD

PHASE 2: DIG PRODUCTION

To de-silt the well and reach the water table, an estimate of 8 meters further depth must be achieved:

Dig Labor Team = $3,500 per square meter x 8 meters

TOTAL DIG LABOR = $28,000 MXN / $1,500 USD

PHASE 3: SOLAR POWERED PUMP + MATERIALS

24 Volt Solar Powered pump + panel kit = $42,885 MXN

5000 Liter Tinaco Rotomex water tank to store the water at height and let it fall by gravity = $12,952 MXN + shipping

Poly Tube 100 meters = $889 MXN

Small Fixtures + Miscellaneous Hardware = $2,000 MXN

TOTAL SOLAR POWER + APPLIANCE COSTS = $58,726 MXN / $3,125 USD

BUDGET TOTAL: $174,962 MXN = $9,300 USD